Infrastructure & Construction

Faster approvals shift risk onto the schedule

Canada is accelerating investment in major infrastructure. The federal Major Projects Office has announced 15 projects representing more than $125 billion in capital investment. The Building Canada Act also provides a framework through which projects designated as being in the national interest can benefit from streamlined federal review and approval processes.

While streamlined review shortens one stage of a project, equipment lead times, material deliveries and crew mobilization run on their own clocks. Projects are still contending with supply chain disruption, workforce constraints and severe weather, often all at the same time.

Accelerated projects often require decisions on long-lead equipment and early works before every downstream dependency has been resolved. That can leave project schedules moving faster than the insurance, financing and risk allocations were originally designed to support. Projects moving ahead on an accelerated timeline should consider whether:

  • Builder’s risk arrangements should be reviewed against the project’s actual start date and scope of early works, particularly where construction activity begins earlier than originally anticipated.
  • Delay-in-startup coverage should reflect the revised critical path. A compressed schedule can increase both the probability and financial consequences of delay, particularly where commissioning, procurement and financing milestones become tightly interconnected.
  • Lenders may revisit insurance requirements if financing milestones and project schedules change.

A project that gains six months in permitting can give that time back just as quickly in procurement. When it does, the key question becomes who bears the cost. The answer usually sits in the contract and the insurance wording.

The shortage is in the trades


Construction's labour market is tighter than the broader labour market. National unemployment held at 6.4% in August,10 but in construction it was 4.7%, and below 4% in some provinces.11

The age profile of recent employment growth also warrants attention. As of August 2026, construction employment among workers aged 55 and older increased by 28,000 year to date, while employment among workers aged 15 to 24 declined by 16,700.12

BuildForce notes that this trend may indicate greater reliance on older, more experienced workers to support project delivery or fill gaps created by contraction among younger workers.

If that pattern persists, it could create longer-term succession and knowledge-transfer challenges, particularly as major projects increase demand for experienced supervisors and specialized trades.

With fewer younger workers entering the industry, there are less people ready to step in as experienced workers retire, just as more major projects move toward construction. And when an experienced supervisor or specialist is injured or unavailable, a project does not simply lose a worker. It loses the person the schedule depends on.

Organizations need to treat labour risk the way they treat supplier risk. A project may look well diversified on paper while still relying on a small group of experienced supervisors, specialized trades or subcontractors whose absence could significantly affect the schedule.

Projects should identify the roles that would be most difficult to replace and where critical knowledge is concentrated. Pairing experienced workers with newer ones can help preserve expertise over time, while strong safety and return-to-work programs can reduce the risk of losing key personnel whose absence could affect project schedules and delivery.


Climate risk now shows up in the schedule


This summer showed how quickly weather can disrupt a project. Eleven severe storm catastrophes were declared across Canada from June onward, with flash flooding driving insured losses in many of them.13

For projects, the issue is less the storm itself and more how the contract and insurance program respond when one occurs. Flood and wildfire sublimits, deductibles, the extent to which delay coverage responds to weather-related disruption, and the number of weather days allowed under the construction contract can all determine how quickly a weather event results in additional costs.

Resilience planning and business continuity capabilities can provide insurers and lenders with a clearer understanding of how a project is prepared to manage severe-weather disruption, rather than relying solely on historical loss experience.

KEY TAKEAWAYS

Faster approvals do not eliminate project delivery risk. As timelines compress, procurement, financing, workforce capacity, insurance and contractual risk allocation need to keep pace. For owners, contractors and lenders, the challenge is ensuring that project assumptions remain aligned with how the work will actually be delivered.

As projects move from approval to execution, several areas deserve closer attention:

01

Making sure coverage reflects accelerated schedules. Builder's risk coverage should begin when the project actually starts, and delay-in-startup coverage should reflect the revised completion timeline rather than the original schedule.

02

Revaluing projects against current costs. A builder's risk value set at contract award may fall short of what a rebuild would cost today, leaving the owner to fund the difference.

03

Identifying critical workforce dependencies. A project may depend on a small number of experienced supervisors, specialized trades or subcontractors whose absence could significantly affect delivery.

04

Testing projects against weather-related disruption. Contracts, schedules and insurance programs should be reviewed to understand how flood, wildfire and severe weather delays would affect costs and completion dates.

10Statistics Canada, September 2026. https://www150.statcan.gc.ca/n1/daily-quotidien/260904/dq260904a-eng.htm

11BuildForce Canada, September 2026. https://www.buildforce.ca/en/blog/women-and-older-workers-drive-national-construction-employment-gains-august-2026-lfs-finds/

12BuildForce Canada, September 2026. https://www.buildforce.ca/en/blog/women-and-older-workers-drive-national-construction-employment-gains-august-2026-lfs-finds/

13CatIQ, August 2026. https://public.catiq.com/2026/08/17/catiq-discloses-second-industry-loss-estimate-for-severe-storm-event-in-ontario-and-quebec-in-june-july-2026/

© 2026 Lockton Companies. All rights reserved.